8th Street Filter Discharge Retention Pond Project

Utility Forces Complete 8th Street Filter Discharge Retention Pond Project

Utility forces, acting as the General Contractor, have completed a percolation pond project that will manage the District’s backwash water for the 8th Street well site filtration system.
The on-site disposal system will eliminate the low threat discharge of backwash rinse water from a drainage pump station inlet.
The project was required as a result of a RWQCB order to eliminate the discharge from entering the drainage system that conveys storm water to the bay.
 

   
The project, estimated at $75,000, was completed in-house by the Los Osos Community Services District Utility crew for under $58,000.

Congratulations!

 